Ash Street Force Main and Pump Station Project

The City of Topeka Utilities Department started construction on the Ash Street Force Main project on April 15th and is scheduled to be completed in April of 2020. The original station was constructed in 1928 with an expansion occurring in 1972. The project consists of construction and installation of a new 48” diameter force main as well as upgrades to the Ash Street Pump Station’s existing pumps, gates, instrumentation and controls. There have been two failures in the existing force main, therefore this is a mandated rehabilitation project as part of the Consent Agreement with the Kansas Department of Health and Environment.
Citizens in the area of the Ash Street Pump Station were notified of the construction by mail this spring. An open house and informational presentation was held on January 24th. The site of construction will have several pieces of large equipment working in the area. The City of Topeka asks that citizens be cautious around the construction work zone. Please follow all temporary construction work zone traffic control which will include detours for vehicular and pedestrian traffic. For more information please contact City Wastewater Engineer Michelle Neiswender at 368-4251.